Other
M56 eastbound jct 9 – 7 lanes three and four closure (MP 26/5 – 17/9)
Road Network: M56 (East bound)
Affected Sectors:
- Sector 1: M56 eastbound between J7 and J6
Status & Certainty: Scheduled Maintenance (Probable)
Restrictions: Mandatory compliance required.
Carriageway & Lane Capacity
- Total Closed Lanes: 2
- Lanes Remaining Open: 1
Schedule Window
- Scheduled Start: 24/08/2026 at 21:00
- Estimated Completion: 25/08/2026 at 06:00
- Schedule data last synced/updated by National Highways on: 18/08/2026 at 01:22